The District of Coldstream is reminding residents and motorists that Aberdeen Road will be closed to through traffic beginning Monday, February 2, 2026, as construction resumes on the Aberdeen sanitary trunk sewer project.
Due to the depth and width of the excavation required for this work, the road closure will be in place 24 hours a day, seven days a week, and is expected to remain in effect until October 1, 2026.
During construction, only local access and emergency vehicles will be permitted within the construction zone.
A safe, signed pedestrian/bicycle corridor will be maintained along the west shoulder of Aberdeen Road for the duration of the project. Please see the included project map for additional context.
ANTICIPATED CONSTRUCTION SCHEDULE
February 2 – February 28, 2026
Construction will take place in the vicinity of the CN Rail crossing.
March 1 – September 30, 2026
Installation of the sanitary sewer main will begin at Whitby Drive and progress north toward Venables Drive. Paving is anticipated to be completed by September 30, 2026.
October 1 – November 30, 2026
Final site restoration, cleanup, and line painting will occur.
Motorists are reminded to use caution when travelling near the construction area and to obey posted signage to ensure the safety of construction crews and the public. This traffic advisory will remain in effect until 6:00 p.m. on November 30, 2026.
For more information, please visit the District’s Project webpage. Residents are also encouraged sign up to receive District News directly to their email.
For construction-related inquiries, including scheduling and traffic management, please contact Chapman Industries at 250-549-2907 (office) or 250-306-7881 (Site Supervisor).